 |
Why
Audit
the Compressed
Air
System?
By Robert B. Laine II
Compressed air systems will almost always
have more power on-line than necessary. How do we know this? For example,
if the average demand (volume) is 1,000-scfm, the demand may vary ±
350-scfm, which requires 1,350-scfm of supply for peaks. Because events
that create the peak are almost instantaneous, supply may have to be
1,500-scfm to maintain a minimum pressure during the event, especially if
there is little storage, and most systems have very little storage.
|
Some compressor
manufacturers recommend no storage for some compressor designs.
Therefore, the norm is to install one 1,500-scfm compressor for a 1,000-scfm
system, that frequently only requires 650-scfm. The 1,500-scfm
compressor will be twice as large as necessary part of the time and 11 %
larger than the peak demand. Most compressors do not trim efficiently,
that is the reduction of power and volume is not linear. Most
compressors will trim volume to match demand, but the power remains at or
near peak as the volume varies. Some designs of compressors do trim
power more efficiently than others.
CAS design has been mostly
influenced by compressor suppliers, whose goal has been to provide a
solution with little or no knowledge of the system outside of the compressor
room. The only reliable solution under these conditions is to make
sure that there is always enough. And with system efficiency not an
issue, the compressor and in most cases multiple compressors will always be
significantly larger than the average demand.

The poorest performing
system with enough on-line power will be fairly reliable, but at a
significant penalty in operating cost. It will not be an efficient
system, but efficiency in compressed air is something that only recently has
become an issue. There is a general trend in the industry to recommend
one large compressor versus several smaller ones, which means that the back
up compressor must be another large unit.
As plant demand grows, the
back up is turned on. An occasional peak slightly greater than
1,500-scfm will turn on the 1,500-scfm back up, which frequently remains on
from that point in time. Now, two 1,500-scfm compressors are required
to support a demand of less than 2,000-scfm. A new compressor is
purchased as back up, and to maintain consistency of equipment and spare
parts, a new 1,500-scfm compressor is installed. Capital cost is based
on 4,500-scfm of compressors and operating cost on 3,000-scfm of
compressors. If the initial design had been three 500-scfm
compressors, the capital cost would be 2,500-scfm (5 x 500-scfm) and the
operating cost would be based on 2,000-scfm. Even with this multiple
compressor arrangement, if there is no knowledge of the system events and
the fifth compressor may be required from time to time.
Installing compressors to
solve a problem inefficiently does not make the compressor manufacturer’s
method or approach bankrupt, since efficiency in the compressed air system
is not part of the agenda of the owner or equipment supplier.
A second issue that makes
for an inefficient system is compressor controls. Remember that the
manufacturer has no knowledge of the system that this compressor will
support as no one from the manufacturer, salesman, or factory
representative, has set foot outside the compressor room. The
compressor is not custom designed for the individual plant and must work in
any system. Therefore, the compressor controls are designed to protect
the compressor, not system efficiency or operating cost. The more
compressors that make up a system, the results are in producing a greater
inefficiency, especially if the compressors are multiple designs (rotary
screws, recips, and centrifugals).
A compressor is an air
pump. When purchasing a liquid pump, a pump curve is provided to the
purchaser by the manufacturer to permit the owner to design around a given
performance standard. Alternatively, the performance requirement is
provided to the manufacturer and the pump is then designed to meet the
performance requirement. This never happens with compressors, and
compressor performance curves are almost never asked for and seldom
provided. Compressor controls limit performance, which is never the
intent with a liquid pump design. For example standard compressors are
equipped with Turnvalves®, Spiral Valves®, blow off
valves, and throttling inlet valves. All of theses devices throttle
the volume to the system, but the power remains relatively constant.
The power of most compressors fully loaded will not be much greater than a
partially loaded compressor. Frequently, multiple compressor systems
will have several, if not all, of the “on” compressors in some state of part
load, but the power will be 75% to 95% of the motor nameplate. This
configuration will become fairly reliable in the sense that there is always
plenty of air supply. As the system pressure decays, the partially
loaded compressors will all load to some degree maintaining supply with a
fluctuation pressure. This is called minimum acceptable results at the
highest operating cost. System pressure can fluctuate an average of 10
to 15-psi with extremes of 20 to 30-psi.
What is a compressed air audit?
An audit is a complete analysis of the compressed air system with the
“system” as the focal point. The supply side of the system
is where the audit starts. How do all of the different pieces of
equipment made by different manufacturers with different standards function
in a system? Most compressor manufacturers make only compressors, but
sell dryers filters, drains, and aftercoolers, all made by some other
manufacturer to fill out their product line. Different manufacturers
will have different standards for differential pressure drop, cooling
performance, drainage standards, etc. The owner is not aware of the
different standards and will frequently purchase from the low bidder, which
means several different brand names will find there way into the compressor
room.
Frequently the system will have perfectly functional equipment that does not
provide the intended result. For example, all standard dryers
(refrigerant and desiccant) are designed for 100 degrees F @ 100-psig.
However, the compressor aftercooler is not functioning appropriately and the
dryer inlet temperature is 115 degrees F, which overloads the dryer by 75%.
There are many performance issues that are frequently ignored and/or not
considered in the design, and for the most part go unobserved by the owner.
The audit will identify all of these issues and make specific
recommendations that will resolve all of these issues. Very specific
recommendations will be made that address all the different designs and how
they can function in a common system. Drawings, written discussions,
and specific performance non-proprietary equipment specifications will be
provided as part of the audit process. The intent is to make
recommendations for retrofit of the system, but at the same time teach a
different philosophy of compressed air that will permit personnel to manage
this utility efficiently. Other utilities have significantly more stringent
standards. For example, would your utilities and production
departments allow a 10 to 20 % fluctuation of electrical system voltage?
Not if they want to keep there jobs, but the plant puts up with this type of
variation with compressed air.
Supply is only half the
system. On the demand side of the system, compressed air is often
wasted and poorly applied. Frequently compressed air is left on when
production stops for breaks, meals, off shifts, or even weekends.
Production equipment frequently consumes air whether production is active or
not and the leaks are supported even if no air is consumed for idle
production. All sources of waste will be identified with specific
solutions provided. Poor application of compressed air frequently can
be moved to another energy source that is less expensive than compressed
air. Specific design recommendations will be provided for these
alternatives.
Many
times alternatives are presented that are inappropriate for specific plants.
The design will be flexible as the audit intent is not to advise the client
what to do, but to present all the alternatives and assist the client in
making the most appropriate decision, which may very well be unique for that
facility. Purchasing the best equipment money can buy in a poorly
defined system will result in a poorly performing system.
Summary:
There are no un-audited
systems that cannot be improved for air quality and performance.
Typical savings in the form of reduced operating cost is 25% to 40%.
The extremes in savings are 10% to 90%. Return on investment averages
less than two years, including the cost of the audit. The extreme
range of return is less than one to three and one-half years. A clean
dry compressed air utility with constant pressure will support every piece
of air consuming equipment more consistently, reliably, and repeatably.
Plant performance and efficiency will improve, which will directly affect
production cost.
Compressed air operating
cost is usually constant regardless of sales and the economy. During a
slow economy, retrofit of the compressed air system can be more attractive
than during the best of conditions. The savings in operating cost from
a retrofitted efficient system goes straight to the pre-tax bottom line with
little or no risk. Frequently, a system retrofit is easier to
implement during a slow economy, but the value to the bottom line will be
the same as during a strong economy. Plant expansion to increase sales
is still dependent on the economy, which has risk. The savings in
operating cost of the compressed air system has no risk.
The greatest savings
opportunity of reduced operating cost in a compressed air system is one that
the owner feels that there are no problems. This system will be
significantly overpowered.
| |
Robert B. Laine II
is a Senior Auditor and President of
Southern Corporation, Augusta, Ga.,
a company specializing in systems auditing and design.
Mr. Laine has been auditing compressed air systems for ten
years, has served more than 100 clients, and has audited over
200 plants ranging from manufacturing to candy production |
|
|